Sumitomo SHI FW Energia Oy, Helen Vuosaari
Ukitig worked six months in 2022 to Sumitomo SHI FW Energy Oy at Helen Oy’s site in Vuosaari biopower plant constructions site. During that time we prefabricated and installed hydraulic pipe lines, temporary blow out pipe system, high pressure air-pipes and burner pipes. Our delivery also contained an ammonia tank, -pipes- and steel structures and silencer’s piping. Ukitig performed all necessary pressure tests and documented all according standards and laws. The scope was 36 person-years in 6 months – a huge project in a short time and our project team did an excellent job there.
Jukka Kerttula
Technical manager, sales
Jukka Kerttula serves as the Technical Manager of Ukitig and is also responsible for the company’s sales. Please don’t hesitate to contact us if you wish to receive further information on Ukitig’s past projects or customer references.